Diamond Track Floor Saw at Derby Bus Station
The project was to renovate the restroom and staff facilities at Derby Bus Station, which necessitated the use of an electric diamond floor saw to remove concrete for the installation of drainage systems for the new staff toilet amenities.
Given the presence of a Premier Inn directly above and the ongoing operations of the Bus Station, measures were essential to mitigate noise, dust, vibration, and sound. Furthermore, as the concrete could not be dismantled using Brokk Demolitions, the substantial blocks were extracted with the assistance of a mini digger.